High School Facilities Next Steps Steering Team
Tuesday, November 20, 2007
7:00 p.m.
Central Administrative Offices Board Room
13780 Hope Street, Brookfield

Approx.
Time

Agenda Item

7:00 1.  Call to Order

7:05

2.  Review/Approve November 14, 2007 and
     November 15, 2007 Minutes

7:10

 

 

 

 

 

 

 

3.  Review Preliminary Information on Five Identified High School Models

  • Conceptual Plans for Remodeling Models
  • Assignable and Total Square Footages for All Models
  • Conceptual (Initial Capital) Cost Projections for All Models
  • Site Implications of One New High School Model

Five Identified Models for Reference

  • Remodel Two Schools
  • Build One New High School (to replace two existing high schools)
  • Build Two New High Schools
  • New Central; Remodeled East
  • New East; Remodeled Central

8:30

 

 

 

4.  Review Other Cost-Related Attributes

  • Updated Cost/Square Foot Comparables for New High Schools
  • Operational Costs for Existing High Schools
  • Capital Asset Replacement Costs for Existing High Schools
  • Updated Cost/Square Foot Comparables for New Construction
  • Financing Costs – Factors and Projections

9:00

 


 

5.  Prepare for November 26 and 29, 2007 Listening Sessions

  • Presentation and Presenters
  • Feedback Format
  • Key Questions

9:20


 


 

6.  Updates

  • Other Communications Topics
  • Date Confirmation for Final Report and Recommendation
  • Steering Team Calendar
  • Future Agenda Items
9:30 7.  Adjournment