High School Facilities Next Steps Steering Team
Wednesday, December 5, 2007
7:00 p.m.
Central Administrative Offices Board Room
13780 Hope Street, Brookfield

Approx.
Time

Agenda Item

7:00 1.  Call to Order
7:05 2.  Review/Approve November 29, 2007 Minutes

7:10

3.  Review Responses from November 26 and 29, 2007 Listening
     Sessions

7:20

 

 

 

 

 

 

 

4.  Review Information on Four Remaining High School Models

  • Conceptual Plans for Remodeling Models at Central and East
  • Feedback from December 4 Tour of West Bend Model
  • Elmbrook Assumptions regarding West Bend Model
  • Assignable and Total Square Footages for all Four Models
  • Conceptual (Initial Capital) Cost Projections for all Four Models

Four Currently Identified Models for Reference

  • Remodel Two Existing Schools (to accommodate 1,150 students each)
  • Build Two New Schools (to accommodate 1,150 students each)
  • Build One New School (to accommodate 2,300 students)
  • Build New Combined Campus School (to accommodate 2,300 students)

8:20

 

 

5.  Review Other Cost-Related Attributes

  • Updated Cost/Square Foot Comparables for New High Schools
  • Financing Costs – Factors and Projections

9:20

 


 

6.  Updates

  • Possible Scheduling of Additional Steering Team Meetings
  • Confirmation of December 11 - Final Report and Recommendation
  • Confirmation of December 17 – Work Session with Board of Education
9:30 7.  Adjournment